Energy drilling with W100 and Tubex, Sweden

Drilling of a 200 meter deep energy well in the central parts of the small town of Söderköping, Sweden. The contractor, Finspång Brunnsborrning AB, chose the water powered Wassara W100 hammer instead of pneumatic technology. The reason was the potentially greater risk of damaging nearby buildings when using a pneumatic hammer compared with the Wassara hammer. Casing drilling was performed for the first 60 meter with Wassara W100 and Tubex.

Result:

Finspångs Brunnsborrning AB successfully carried out the drilling operation without causing any damage to surrounding buildings.

Equipment:

Hammer

Wassara W100

Bit

Tubex

Pump

Rinsing truck

Drilling fluid

Clean water

Drill pipe

3000 mm, OD 102 mm and 6,3 mm wall thickness

Rig

Nemek

Formation

Sand and silt, water in the formation