Case study about drilling in the Angostura dam in Chile published
The bedrock below the Angostura Hydroelectric Plant needed water-proofing, this was done by drilling 64 mm holes and then grouting with cement. The allowed borehole deviation was set to 2% at full length. Wassara managed to meet the requirement by far.