The Stockholm Central station has been sinking 1 mm per year and needed reinforcement of the foundation. This was done by drilling and setting casing all the way down to the bedrock.
Niches were cut out from the side of the existing foundation walls, big enough to allow access for a small drill rig. Wassaras water-powered DTH hammer was prescribed for the project as the environment was sensitive in several ways.
Foundation reinforcement
The landlord Jernhusen hired the construction and project management company Forsenprojekt for the reinforcement project. The contractor Lemminkäinen was awarded the contract for the later part of the foundation works. This part of the project included the installation of 428 steel piles, placed every second meter in the foundation wall and down into the bedrock. The sensitive environment demanded as benign drilling as possible. No noisy machinery or dust in the air was allowed. Any vibrations must be kept at a minimum. The water-powered drilling with Wassara is the only percussion drilling technology that meets these demands.
A project with many particular demands
As parts of the building are listed as a National Heritage, strict national laws applies; the building must not be damaged. The available workspace for the operation was quite cramped, due to bulky foundation walls. To further complicate the works, multiple parallel construction projects were running at the same time.
As the public area was in full operation, some 200 000 commuters were passing very close to the drill site every day. This pushed the environmental aspects with low noise even further. It also made the moving of drill rigs and other machinery limited to off-peak hours.
Drilling inside the foundation walls
Niches were cut out from the side of the foundation walls, big enough to allow access for a small drill rig. The drilling and casing advancing was done all the way down to the bedrock, an average of 16 meters. The formation was full of oak logs that had to be drilled through. After the casing was set, arrangements were made in the walls to enable the support of the new pillars. This was repeated every second meter of the wall.
Creating new space
The Central station’s lower hall accommodates several stores and small shops. In order to create more space, the number of the rather bulky foundation walls needed to be minimized in this area. Some 3 600 m2 of new area has been created in the lower hall. This was achieved by excavation of new areas and lowering of the floor level, as well as replacing bulky walls with supporting steel pillars.